Last Monday, PEL and Trihope sign on the installation satisfaction for 1200KV, 180KJ High voltage impulse generator system. This is a new stage for M/S PEL. Because it means she has the ability to ...
A series of problems, such as larger diameter, the formation of waves on the cylinder, the deviation of the verticality of the assembly, and the unqualified performance after annealing during proce...
Q1) what are instrument transformer?
If we want to measure extremely high values of current and voltage than there are two ways of measuring it. One is to use high capacity instruments which would ...
I.Cause of Partial Discharge
The transformer insulator, metal body and so on are often with some sharp angle and burr, so the electric charges under the action of electric field intensity will conc...
Total eight sets of machines and equipment from Mexican customers have been delivered for use one after another. Thank all partners for your strong support! Work together for Chinese equipment goin...
China, Sichuan: China is building an ultra-high voltage substation at the highest altitude in the country so far.
The construction of a 1,000 kV substation in Ganzi Tibetan Autonomous Prefecture of...